Process Flow
INFOGRAPHIC
1
Design Flow
2
Construction Flow
⚫
⚫
⚫
⚫
⚫
⚫
⚫
⚫
•
Preliminary
Phase 1
Kick Off
Phase 2
Schematic
Phase 3
Design Development
Phase 4
Contract Documentation
Phase 5
Construction Implementation
Phase 6
Handover
Phase 7
Final Account
Construction Flow
Preliminary
01
Enquiry from client
With scope of work
ID
Architecture
Landscape
Size of area
Date expect to move in
Budget
Layout available? ✅
If layout not available, ENDO can perform BASIC measurement
02
ENDO prepare Professional Design Fee
Quotation detailing scope & terms of payment
Note
:
We don't prepare free design upon confirmation
Construction quotation is not provided at this stage
Client Accept
Deposit payment made to secure waiting list*
To sign on Design Agreement
Client Reject
Process End
* Waiting list is subject to ENDO current workload
Phase 1: Kick Off
01
Kick off meeting
(i) Finalise Design Agreement with
lawyer based on agreed scope of work
(ii) It’s best to finalise the design agreement during the waiting period
02
Kick off meeting
(i) Taking the Client’s instructions and analyzing the project brief; and
(ii) Site visit and site investigation
Phase 2: Schematic
Archi
Layout arrangement
Space planning
Building massing
Material visual
ID
Moodboard
Furniture layout arrangement
Material visual
Landscape
Moodboard
Landscape massing
Material visual
Vision Package
Based on the scope selected by client, the following items will be combined together and presented to the client as
Vision Package
Vision package is the Designer’s Vision of the project. This process will require feedback from client and signed off before moving to Phase 3
Client is entitled for amendments up to 3 times free of charge at every stage of commencement and phases
Note
:
Based on agreement. Completion of schematic Phase will render client to sign off and make payment
Schematic Design Visual Reference
Phase 3: Design Development
Based on agreed scope of works, the approved Design Intent by client will comprise of:
Archi
3D Artist Impression
Detail drawings
GA Drawings
Prepare submission drawing
ID
3D Artist Impression
GA Drawings
Prelim material selection
Landscape
3D Artist Impression
GA Drawings
Prelim Material selection
Civil
Structure Design Drawings
Geotech design
Prepare submission drawings*
M&E
Prepare M&E drawings
Preselect light fittings
Additional
:
Estimate cost plan - not to be used as final cost plan
3D Artist Impression Reference
Design Intent Visual Reference
Note
:
Also this stage will take up 2-3 meetings before finalize by client, and will not move to the next stage until client signed off
Based on agreement. Completion of DD Phase will render client to make payment
Phase 4: Contract Documentation
01
The Contract Documentation stage is to document the concept/idea from phase 2 and 3 into tender drawings, with
technical, material and specifications
Note:
Cost estimation will also be updated in this phase. However, it is not as final cost
02
Contract Documentation
Who will build? (3 options)
Option 1
ASCORE
ENDO sister company
Option 2
DIRECT AWARD
Client own appointed contractor
ENDO scope as consultant
Option 3
TENDER PROCESS
ENDO scope as consultant
ENDO will:
Call for 3 company (max) for tender
Conduct tender interview
Prepare for tender report
Award on behalf of client
If required ENDO will assist Quantity Surveyor to complete the Bill of Quantity (BQ)
* Up to 3 contractors for tender process
Contract Implementation
Note:
Based on agreement. Completion of Phase 4 will render client to make payment
Phase 5: Construction Implementation
The process of moving from documentation phase to realising the works at site
1
Conduct site kickoff meeting with maincon and consultants
2
Prepare site memo
3
Inspect maincon work
4
Attend to site meetings and conduct site visits (once or twice a month)
5
Prepare CPC when practically completed
Note:
Further detail in the agreement
Furniture hunting will be during this stage
Phase 6: Handover
1
ENDO will perform defect checking at site
2
Issue CCC (certificate completion & compliance)
Phase 7: Final Account
1
After the completion of DLP, ENDO will issue CMGD (Cert of Make Good Defect)
2
Prepare and submit final account to client
Construction Flow By ASCORE SB (ASB)
Pre Construction
ASB to receive the drawing and spec from designer and prepare (Bill of Quantity) BQ and timeline
During Construction
ASB at Implementation stage, will have periodic on site meetings.
To supervise, manage, and monitor site
Post Construction
ASB with client to do one time defect check based on BQ.
ASB to perform and rectify the defects.
ASB will prepare and submit Final Acc
Pre Construction
During Construction
Post Construction
ASB to receive the drawing and spec from designer and prepare (Bill of Quantity) BQ and timeline
ASB at Implementation stage, will have periodic on site meetings.
To supervise, manage, and monitor site
ASB with client to do one time defect check based on BQ.
ASB to perform and rectify the defects.
ASB will prepare and submit Final Acc
Note:
1. Variation Order (VO) that will result in additional cost; ASB shall prepare new BQ
2. VO shall be paid in full upon invoice and the said payments does not fall within the original progress payments.
3. Works by other contractor not within ASB scope of work, ASB is not responsible.